G702 and G703 software: fill out the application and continuation sheet online

The G702 is a one-page summary; the G703 is the line-by-line continuation sheet behind it. Every number on the G702 comes from the G703, so if you get the sheet right the summary is automatic.

By Vagish Kapila, founder of Varshyl Inc. and a licensed California general contractor · Updated 2026-11-16

The two documents, in one paragraph each

The continuation sheet (G703 format) lists every line item from your schedule of values with nine columns: item number, description, scheduled value, work completed from previous applications, work completed this period, materials presently stored, total completed and stored to date, percent complete, balance to finish, and retainage. Its totals feed the summary.

The application and certificate for payment (G702 format) is the cover page: original contract sum, net change by change orders, contract sum to date, total completed and stored to date, retainage, total earned less retainage, less previous certificates for payment, current payment due, and balance to finish including retainage. It is signed by the contractor, notarized on many jobs, and certified by the architect.

Note on the names: G702 and G703 are document numbers from a widely used family of standard construction forms. Most owners and lenders ask for "a G702/G703" meaning that layout and arithmetic. SOVIQ produces applications in that format; it does not sell the licensed paper forms, and if your contract requires the official forms you can copy the numbers across in minutes.

The continuation sheet, column by column

ColumnMeaningWhere it comes from
A. ItemLine numberYour schedule of values
B. DescriptionWhat the line coversYour schedule of values
C. Scheduled valueDollar value of the lineYour schedule of values (plus approved change orders)
D. From previous applicationEverything billed on this line through last monthColumn G of last month's sheet
E. This periodWork put in place this monthYou
F. Materials presently storedDelivered, on site or in bonded storage, not yet installedYou, with backup
G. Total completed and stored to dateD + E + FCalculated
%G ÷ CCalculated
H. Balance to finishC − GCalculated
I. RetainageUsually 5% or 10% of G (sometimes a different rate on stored materials)Calculated

The mistake that gets most applications rejected: column D next month must equal column G this month, line for line. When someone retypes it, it drifts.

A worked example

Say a $420,000 contract with a line "Rough carpentry, $96,000." Through last month you billed $48,000 on that line (50%). This month you installed another $19,200 of work and have $6,000 of lumber stored on site.

ColumnValue
C. Scheduled value$96,000
D. From previous$48,000
E. This period$19,200
F. Stored$6,000
G. Total to date$73,200
% complete76.25%
H. Balance to finish$22,800
I. Retainage at 10%$7,320

Do that for every line, total the columns, and the G702 cover page fills itself: total completed and stored to date is the sum of G; retainage is the sum of I; less previous certificates is last month's "total earned less retainage"; current payment due is the difference.

Filling it out online vs. the spreadsheet

Most contractors still do this in Excel. It works until a line gets inserted, a change order shows up mid-month, or the previous-billing column gets pasted one row off. Software that holds the schedule of values and carries the previous column forward automatically removes the three errors that cause rejections: carry-forward drift, retainage computed on the wrong base, and change orders that changed the contract sum but not the line items.

With SOVIQ, you upload the schedule of values once (PDF, Excel or Word; it reads the file), enter this period's progress and stored materials each month, and it produces both documents, carries everything forward, and keeps the approved change orders reconciled. The AI reads what you upload and checks the math before you submit.

Frequently asked

Is G702 the same as a pay application?

A pay application is the whole package; the G702 is the summary page in the most common format for it, with the G703 continuation sheet behind it.

Do I need the official forms?

Only if your contract says so. Many owners accept any application that follows the same layout and math. If yours requires the licensed forms, generate the numbers in SOVIQ and transfer them.

Where do change orders go on the G702?

In "net change by change orders," which adjusts the original contract sum to the contract sum to date. Each approved change order also becomes one or more lines on the continuation sheet so it can be billed.

How is retainage shown?

On the continuation sheet as a column against each line, and on the summary as a total that is subtracted from total completed and stored to date before previous payments are deducted.

Produce G702/G703-format applications without the spreadsheet

Upload your schedule of values, bid or proposal and SOVIQ produces the pay application, continuation sheet and change orders for you. $150 a month, AI included.