How to fill out a pay application, line by line
A pay application has about a dozen numbers that matter and three that reviewers check first. Here is the order to fill them in, what each one means, and a full example you can follow with your own job.
Before you start: what you need on the desk
- The approved schedule of values for the contract.
- Last month's application, approved, including its continuation sheet.
- A list of approved change orders to date, with amounts.
- Your progress by line for this month (percent or dollars), with backup: photos, quantities, delivery tickets.
- Stored materials on site or in bonded storage, with invoices.
- The contract's retainage terms (rate, whether it applies to stored materials, any cap).
Step 1: Fill the continuation sheet first
Work line by line down the schedule of values.
- Scheduled value (C): from the SOV. If a change order added to this line, use the adjusted value; new change orders get their own lines at the bottom.
- From previous application (D): copy column G, total completed and stored to date, from last month's sheet. Not column E. This is the number reviewers check first.
- This period (E): work put in place since last month, in dollars. If you track percent, multiply the percent gained by the scheduled value.
- Materials presently stored (F): delivered but not installed, with invoices. When material is installed, it moves from F into E.
- Total completed and stored to date (G): D + E + F.
- Percent (G ÷ C).
- Balance to finish (H): C − G.
- Retainage (I): G × the contract's retainage rate (check whether stored materials carry a different rate).
Total every column at the bottom.
Step 2: Fill the application (cover page)
- Original contract sum: from the contract.
- Net change by change orders: sum of approved change orders to date, additive and deductive.
- Contract sum to date: 1 + 2. It must equal the total of column C.
- Total completed and stored to date: the total of column G.
- Retainage: the total of column I (shown separately for completed work and stored materials if the rates differ).
- Total earned less retainage: 4 − 5.
- Less previous certificates for payment: line 6 from last month's application.
- Current payment due: 6 − 7. This is the check you are asking for.
- Balance to finish, including retainage: 3 − 6.
Then the change order summary box (additions and deductions, this month and previous), the contractor's signature, notary if required, and the architect's certification.
Worked example
Contract: $420,000, one approved change order of +$12,500, 10% retainage. Three lines shown; a real sheet has thirty to sixty.
| Line | C Sched. value | D Previous | E This period | F Stored | G Total to date | % | H Balance | I Retainage |
|---|---|---|---|---|---|---|---|---|
| Mobilization | $14,000 | $14,000 | $0 | $0 | $14,000 | 100% | $0 | $1,400 |
| Rough carpentry | $96,000 | $48,000 | $19,200 | $6,000 | $73,200 | 76.25% | $22,800 | $7,320 |
| CO-01 Added canopy | $12,500 | $0 | $5,000 | $0 | $5,000 | 40% | $7,500 | $500 |
Suppose the whole sheet totals: C $432,500 · G $261,300 · I $26,130. Last month's total earned less retainage was $198,540.
| Cover page | Amount |
|---|---|
| 1. Original contract sum | $420,000 |
| 2. Net change by change orders | $12,500 |
| 3. Contract sum to date | $432,500 |
| 4. Total completed and stored to date | $261,300 |
| 5. Retainage (10%) | $26,130 |
| 6. Total earned less retainage | $235,170 |
| 7. Less previous certificates | $198,540 |
| 8. Current payment due | $36,630 |
| 9. Balance to finish incl. retainage | $197,330 |
The three checks a reviewer runs first
- Column D on this sheet equals column G on last month's sheet, line for line.
- Line 3 equals the total of column C, and the change order box matches the approved change orders.
- Line 7 equals last month's line 6.
If those three pass, the review moves to whether the percentages are believable. Attach photos and quantities for any line that jumped more than 25% in a month.
Doing it in software instead
Every step above is arithmetic on last month's numbers plus this month's progress. SOVIQ holds the schedule of values, fills D from last month's G automatically, applies the contract's retainage rules, keeps change orders reconciled and produces both pages. You enter E and F; it does the rest and reads your uploaded documents to check them. $150 a month, AI included.
Frequently asked
What goes in "this period" if I installed material that was billed as stored last month?
Move it: reduce stored (F) by the installed amount and add it to this period (E). Total to date (G) only changes by new work.
Can I bill 100% of a line before it is inspected?
You can bill what is complete, but many owners cut lines back until inspection. Bill to what you can defend with backup.
What if the owner changed the retainage rate mid-job?
Apply the new rate from the effective date forward and show the two retainage totals separately on the cover page; note it in the application.
How long does the owner have to pay?
Whatever the contract says, often 30 days from certification. Prompt-payment statutes in many states set a maximum. Track days-to-pay by owner; it predicts next month better than the contract does.